Project Bankability
Project finance is a powerful mechanism for mobilizing long-term investment in infrastructure, industrial development, and public services. It is commonly employed in capital-intensive sectors such as energy, construction, oil and gas, transportation, and broader infrastructure development.
Unlike traditional corporate financing, which relies heavily on the creditworthiness of the borrowing entity, project finance is structured around the viability of the project itself. Repayment is primarily sourced from the project’s future cash flows, while the project’s assets, contracts, and rights are used as collateral. This model typically involves the establishment of a Special Purpose Vehicle (SPV), a legal entity created solely for executing the project, thereby limiting or eliminating recourse to the sponsor’s balance sheet. The emphasis thus shifts from “who is borrowing” to “what is being built.”
However, securing project finance goes beyond presenting a compelling business case. It requires instilling confidence in investors and lenders that the project will deliver reliable, sustainable performance over the long term. This confidence centres on a single, defining principle: bankability.
In the realm of project finance, bankability marks the line between a promising idea and an investable opportunity. A project is deemed bankable when its commercial, legal, regulatory, and technical risks are clearly identified, equitably allocated, and effectively mitigated. The goal is not to eliminate risk altogether, but to ensure that risks are transparent, foreseeable, and managed in a manner that aligns the interests of all stakeholders involved.
This concept is especially critical in developing markets such as Ethiopia, where institutional reforms and economic liberalization are opening new frontiers for investment in sectors including infrastructure, banking, telecommunications, and energy. Interest from both domestic and international sponsors is growing, driven by the government’s Homegrown Economic Reform Agenda, which prioritizes private sector engagement and is supported by recent legislative and policy shifts.
Key reforms, such as the liberalization of the foreign exchange regime and proposed amendments to land ownership laws, further signal a strong governmental commitment to creating a more predictable and investor-friendly environment. Yet, translating this momentum into actual investment requires more than ambitious policy frameworks. It demands bankable, well-structured, and legally sound projects that can withstand the scrutiny of financiers and deliver long-term value.
This article, the first in a three-part series, explores the foundational considerations that influence project bankability. It lays the groundwork for the subsequent instalments, which will delve into legal structuring techniques in project finance in Ethiopia and examine the persistent “guarantee gap” that often impedes financial closure in capital-intensive sectors.
Bankability Benchmarks
- Stable and Predictable Revenue Stream
At the heart of any bankable project lies the certainty and predictability of its revenue stream. For lenders and investors, the central question is whether the project will reliably generate long-term cash flows sufficient to service debt, sustain operations, and deliver acceptable returns on investment. In project finance structures, where recourse to sponsors’ balance sheets is limited or non-existent, cash flow becomes the sole repayment source. The strength and reliability of a project’s revenue stream directly influence financing terms, risk premiums, and investor appetite. This revenue predictability can be seen from different interrelated elements:
- Source of Revenue: Projects may derive income from user-pay mechanisms, such as tariffs, tolls, and service charges, common in sectors like transport, water, electricity, and health infrastructure. These models depend on demand certainty, pricing regulation, and end-user willingness and ability to pay. Alternatively, many infrastructure projects, particularly those developed under Public-Private Partnership (PPP) arrangements, may rely on government-backed payments, such as availability payments or output-based subsidies. These are typically more bankable when underpinned by sovereign guarantees or secured through multi-year fiscal commitments. Another widely used structure, especially in energy and industrial projects, is the offtake agreement, such as Power Purchase Agreements (PPAs), which provide long-term (15–25 years) cash flow certainty when concluded with creditworthy counterparties. These contracts are often denominated in hard currency and designed with indexation mechanisms to preserve real value.
- Reliability of the counterparty: Revenue structure alone is insufficient without a credible payer. The reliability of the counterparty, whether a sovereign, state-owned enterprise (SOE), private off taker, or multilateral institution, is paramount. While sovereigns generally offer higher creditworthiness, liquidity challenges at the sub-national or SOE level in many developing countries, including Ethiopia, necessitate credit enhancements like escrow accounts, reserve facilities, or guarantees from development finance institutions (DFIs). In cases where corporate off takers are involved, rigorous credit due diligence and the use of instruments such as letters of credit are essential. The involvement of multilateral development banks (MDBs), either as co-financiers or counterparties, typically enhances investor confidence and signals adherence to international project standards.
- Revenue volatility and demand risk: Notwithstanding a well-structured revenue source and a credible payer, projects remain exposed to revenue volatility and demand risk, which can destabilize cash flow projections. Price risk may arise from fluctuations in input costs (e.g., fuel), especially in the absence of robust tariff indexation or regulatory stability. Volume risk is common in projects tied to consumption patterns or user fees, such as toll roads or mobile tower leasing, and can be mitigated through minimum revenue guarantees or shadow tariffs. Further, projects vulnerable to seasonality or environmental events, such as hydropower or agriculture, require contractual risk-sharing mechanisms and insurance protections to absorb income shocks from force majeure events.
- Currency convertibility and repatriation: A particularly acute concern in emerging markets is currency convertibility risk. Many projects are structured with debt or equity denominated in hard currency, while revenues are earned in local currency. In Ethiopia, this mismatch has been a recurring concern, particularly given the birr’s historical depreciation and limited access to foreign exchange. To mitigate this, developers commonly use index-linked tariffs, foreign currency reserve accounts, or government guarantees to hedge forex exposure. Significant reforms have recently been undertaken by the National Bank of Ethiopia (NBE), including under Foreign Exchange Directive No. FXD/1/2024, which introduced a market-driven exchange regime, allowed exporters to indefinitely retain 50% of their foreign exchange earnings, and increased advance payment thresholds for importers. These measures have reportedly boosted foreign reserves to USD 3.6 billion and reduced the parallel market premium to below 10%. Importantly, the directive introduced a transformative provision enabling foreign investors in large-scale projects to open offshore bank accounts. This change directly mitigates convertibility and repatriation risks that have long undermined Ethiopia’s investment climate. The ability to ring-fence revenues offshore enhances investor control over cash flows, facilitates complex financing structures, such as escrow, waterfall, and debt service reserve mechanisms, and significantly reduces the risk premium associated with capital repatriation delays or forex shortfalls. The Directive further introduced the concept of convertibility guarantee which directly addresses the currency convertibility risks of such large-scale investments. This reform aligns Ethiopia more closely with international project finance practices and has the potential to unlock new investment flows into capital-intensive sectors.
- Legal and regulatory backing: In regulated sectors like energy, water, and transport, the transparency and credibility of tariff-setting mechanisms are essential. Political interference, tariff suppression, or opaque adjustment procedures can erode confidence in revenue forecasts. In Ethiopia, long-term PPAs with state utility Ethiopian Electric Power (EEP) have historically included government-backed payment undertakings, but investors have cited challenges related to forex availability and institutional delays. Recent reforms, such as the introduction of competitive tariff structures, legal recognition of termination compensation under the PPP framework, and increased arbitration protections under Proclamation No. 1237/2021, represent important steps toward reinforcing contractual predictability. As Ethiopia continues to expand its capital-intensive infrastructure ambitions, the coherence between revenue streams, payer reliability, risk mitigation structures, currency access, and enforceable legal frameworks will ultimately determine the extent to which projects can move from conceptual design to financial close.
- Proper Risk Allocation Among Stakeholders
Efficient risk allocation is foundational to project bankability. Risks must be assigned to the party best equipped to manage them. This principle enhances creditworthiness and fosters alignment between public and private stakeholders.
Globally, risks such as construction, operation, demand, and currency fluctuation are carefully negotiated across contracts. For example, construction risks are typically shifted to the private sector via fixed-price, date-certain EPC contracts. Operational risks are managed through performance-based operations and maintenance (O&M) agreements. Market or demand risks are mitigated via offtake agreements or revenue guarantees, while foreign exchange and political risks are addressed through sovereign guarantees or multilaterals’ partial risk guarantees (PRGs).
In Ethiopia, Proclamation No. 1076/2018 and its PPP Directive establish the legal foundation for risk allocation. The framework allows for direct negotiation in strategic or unsolicited projects, defines government support mechanisms, and provides clarity on risk-sharing modalities. This structured approach has enabled significant transactions, such as the 300 MW Aysha Wind Power Project developed by AMEA Power. The project secured over USD 600 million in investment, underpinned by a long-term power purchase agreement and government guarantees.
Comparative African experience reinforces this. In Senegal, the 158 MW Taiba N’Diaye Wind Project succeeded due to well-structured risk allocation and PPA terms backed by sovereign support.
- Enforceable Legal and Contractual Arrangements
Even financially viable projects will fail to attract investment if their legal and contractual foundations are not enforceable. Investors and financiers must be confident that rights can be upheld through impartial, predictable, and timely mechanisms.
This includes the enforceability of project documents such as concession agreements, PPAs, offtake contracts, and security arrangements (e.g., mortgages, pledges, or step-in rights). Ethiopia has made notable progress in this regard. Proclamation No. 1237/2021 modernized arbitration laws and brought Ethiopia in line with the New York Convention. The Movable Property Security Rights Proclamation No. 1147/2019 further expanded the scope of enforceable collateral.
However, an “enforcement gap” persists. Judicial processes remain protracted, with average contract enforcement taking over 530 days. Immovable property foreclosure still requires lengthy court involvement, diminishing the practical value of collateral. Arbitration remains the preferred avenue for cross-border transactions, but judicial recognition and enforcement mechanisms must further mature.
Successful African jurisdictions have addressed these issues head-on. Rwanda, for instance, established commercial courts with trained judges and fast-track procedures, dramatically improving contract enforcement. Ethiopia’s recent reforms are promising but will need sustained institutional strengthening to match such efficiency.
- Regulatory and Political Stability
A stable and predictable regulatory environment is essential for long-term project viability. Investors assess not only the existing legal regime but also the likelihood of abrupt or adverse policy shifts. This is particularly relevant in areas such as tariff setting, licensing, land rights, taxation, and foreign currency regulation.
Regulatory unpredictability increases the cost of capital and discourages private investment. A history of abrupt legal or administrative changes can deter long-term financing. Ethiopia has demonstrated positive intent through legislative reforms and liberalization efforts, but consistency and institutional capacity must be maintained to uphold investor confidence.
- Technical, Financial, and Environmental Feasibility
Feasibility studies form the backbone of any bankable project. These studies must rigorously assess technical design, financial structure, and environmental/social impacts. A sound technical plan conoffices that the project can be implemented within scope and cost. Financial models must demonstrate adequate cash flow, realistic assumptions, and sustainable debt service ratios.
Environmental and Social (E&S) considerations are now central to investment decisions. The new Environmental and Social Impact Assessment (ESIA) Proclamation No. 1317/2025 mandates assessment of social and cultural impacts alongside environmental ones. Projects must also align with international benchmarks, such as the IFC Performance Standards and AfDB safeguards.
Many international financiers will not proceed without robust E&S mitigation frameworks. This is evident in large-scale African projects such as South Africa’s REIPPPP (Renewable Energy Independent Power Producer Procurement Programme), which integrated ESG compliance from project inception, resulting in successful financial close across multiple renewable energy projects.
Effective feasibility assessments also support lifecycle planning, demand forecasting, and risk-adjusted revenue modelling, crucial for structuring layered financing and ensuring long-term sustainability.
Conclusion
Ethiopia stands at a critical juncture where the ambition to scale infrastructure and industrial development must be matched by a deep understanding of project bankability. As outlined in this article, ensuring stable and predictable revenue streams, fair risk allocation, enforceable contractual frameworks, regulatory certainty, and robust feasibility assessments are essential preconditions for mobilizing long-term finance. While recent reforms, such as those in foreign exchange management and public-private partnership frameworks, are encouraging, sustained implementation and investor confidence will hinge on how these principles are operationalized in real transactions. This article is the first in a three-part series exploring project finance in Ethiopia; upcoming instalments will delve into legal structuring techniques and the role of guarantees in unlocking capital for bankable, high-impact projects.
This article is general information and not legal advice. Contact us about your specific situation.